Hernando Beach dredging consultant asks for extra payments
Project Updates - February 5, 2010
Hernando Today reports that a dredging consultant working on the Hernando Beach project, Halcrow Inc, has submitted two change orders totaling US$794,130 to complete operations at Hernando Beach.
The delay in the start-up of dredging operations has affected the overall construction schedule, according to a memo sent late Wednesday from Halcrow to Director of Public Works Susan Goebel.
Hernado Today said the first change order from Halcrow is for US$634,300. In a memo, Halcrow said it needs the extra money to complete on-site seagrass mitigation and to institute a series of de-watering systems mandated by the Florida Department of Environmental Protection.
In a separate request, Halcrow is asking for commissioners' approval for an eighth change order totaling US$159,830 to cover the costs of seagrass monitoring.
Instead of calling it a change order, Halcrow calls it a "supplemental agreement."
Halcrow is projecting the completion of the dredge project to be the end of May rather than the originally agreed-upon date of mid-March.
More articles from this category
More news
- International seminar on dredging and reclamation coming to Singapore again
Dredging Organisations - August 13, 2020 - Maintenance Dredging, Dismal Swamp Canal and Feeder Ditch, Chesapeake, Virginia - Award
Contracts & Tenders - September 9, 2010 - MAINTENANCE DREDGING, 6FT FEDERAL CHANNEL, PAWTUXET COVE, RI - PRE-SOLICITATION
Contracts & Tenders - September 9, 2010 - TOPSIDE REPAIRS TO DREDGE WHEELER - AWARD
Contracts & Tenders - September 8, 2010 - Maintenance and Improvement Dredging of Bucks Harbour, Machiasport, Maine - Solicitation
Contracts & Tenders - September 8, 2010 - Brazos Island Harbour, Texas - Pipeline Dredging - Sources Sought
Contracts & Tenders - September 8, 2010 - Hidrovia waterway to be dredged
News - September 8, 2010 - Former manager gets prison term for dumping dredge spoil
News - September 8, 2010 - Great Lakes Dredge & Dock Corporation announces management changes
News - September 8, 2010 - Public comment period opens for proposed Duxbury Harbour dredging project
Project Updates - September 8, 2010 - Petron dredging Marikina River
Project Updates - September 7, 2010 - Thailand's Nan River to be dredged
News - September 7, 2010 - Papers invited for CEDA Dredging Days 2011
News - September 7, 2010 - HollandMT and C-Job collaborate on new trailing suction hopper dredgers
New Vessels - September 7, 2010 - IHC Engineering Services and Liebherr-France to collaborate on backhoe dredgers
News - September 6, 2010